Filters
Question type

Study Flashcards

A breach of contract is said to have occurred only if both the parties do not perform their duties as specified in the contract.

Correct Answer

verifed

verified

________ damages are awarded when the nonbreaching party sues the breaching party even though no financial loss has resulted from the breach.


A) Consequential
B) Compensatory
C) Nominal
D) Liquidated

Correct Answer

verifed

verified

An arbitration agreement separate from the actual contract cannot be enforced on a breach of contract.

Correct Answer

verifed

verified

A professional baseball player signs a three-year contract with a baseball team.Six months into the contract,the player breaches the contract.Sighting this opportunity,another team induces the player to join them.Under these circumstances,is the new team liable to the first team for the tort that arises?

Correct Answer

verifed

verified

No,a third party can contract with the b...

View Answer

Rescission and restitution restore the parties to the positions they occupied prior to the contract.

Correct Answer

verifed

verified

Which of the following constitutes material breach?


A) inferior performance
B) substantial performance
C) anticipatory repudiation
D) rescission without notification

Correct Answer

verifed

verified

Which of the following torts arises when a third party induces a contracting party to breach the contract with another party?


A) intentional interference with contractual relations
B) breach of the covenant of good faith and fair dealing
C) tort of bad faith
D) malicious breach of contractual relations

Correct Answer

verifed

verified

A court order that prohibits a person from doing a certain act is termed as a(n) ________.


A) rescission
B) reformation
C) injunction
D) restitution

Correct Answer

verifed

verified

________ occurs when one contracting party informs the other that he or she will not perform his or her contractual duties when due.


A) Restitution
B) Rescission
C) Anticipatory repudiation
D) Accommodation

Correct Answer

verifed

verified

Liquidated damages are enforceable if ________.


A) actual damages are difficult to determine
B) they are excessive or unconscionable
C) the damage is considered to be a penalty
D) damages do not result in a loss of money to the nonbreaching party

Correct Answer

verifed

verified

Monetary damages cannot be recovered for minor breach of contracts.

Correct Answer

verifed

verified

Mary buys a new toaster for $500.The toaster's label bears a disclaimer stating that the manufacturer is not liable for consequential damages.On Monday morning,while Mary is using the toaster,it emits sparks and damages the electric wiring in the kitchen.The electrician tells Mary that the toaster malfunctioned and that the cost of repairs in her kitchen would come up to $2,000.What can Mary recover from the manufacturer of the toaster?


A) $500
B) $2,500
C) $2,000
D) no damages can be recovered

Correct Answer

verifed

verified

If a contractual duty has been discharged,the contracting party owes an absolute duty to perform the duty.

Correct Answer

verifed

verified

Which of the following is true of anticipatory breach?


A) It occurs when a contracting party fails to inform the other party in advance about non-performance of his or her contractual duties when due.
B) In case of anticipatory breach, nonbreaching party's obligations under the contract are not discharged.
C) The nonbreaching party must wait till performance is due to sue the breaching party.
D) It can be derived from the conduct of the breaching party without being expressly stated by that party.

Correct Answer

verifed

verified

If a breaching party refuses to pay the judgment of a contract breach,the nonbreaching party can seize the properties of the breaching party without a court order.

Correct Answer

verifed

verified

A third party can be sued for intentional interference in spite of him or her having no knowledge of an existing contract between two parties.

Correct Answer

verifed

verified

An anticipatory breach of contract excuses the nonbreaching party from mitigating damages.

Correct Answer

verifed

verified

Brooksold Corporation contracts to have Zealent Construction Company build a factory for $4,000,000.Days before the start of construction,Zealent withdraws from the contract.Brooksold invites proposals for the construction and contracts with Sierra Nos Builders for $3,800,000.Can Brooksold hold Zealent liable for nonperformance? What can the company recover as compensation for damages?

Correct Answer

verifed

verified

If the builder breaches a construction c...

View Answer

In an intentional interference with contractual relations,a third party can contract with a breaching party without becoming liable for this tort if a contracting party has already breached the contract.

Correct Answer

verifed

verified

An award of ________ orders the breaching party to complete the acts promised in a contract.


A) reformation
B) injunction
C) restitution
D) specific performance

Correct Answer

verifed

verified

Showing 41 - 60 of 100

Related Exams

Show Answer