Filters
Question type

Study Flashcards

The difference between projects that fail and those that are ultimately successful has to do with:


A) The plans that have been made to deal with problems as they arise.
B) The fact that a successful project doesn't encounter problems.
C) Whether the project is for an internal or external customer.
D) Whether the problem is time- or budget-related.

Correct Answer

verifed

verified

Which of these statements about the project risk analysis and management program is BEST?


A) Risk management is best handled using an ad hoc approach.
B) If a choice between accepting and transferring risk presents itself, risk should be transferred.
C) The project manager should choose a small subset of all risk management tools.
D) Multiple approaches to risk management should be integrated into a coherent, synthesized approach.

Correct Answer

verifed

verified

Based on the projected selling price of $20 per unit, the manufacturer invested a substantial portion of its available cash in a machine that could produce twenty-thousand gumballs in an hour. If consumers weren't willing to pay this much for gum, then the manufacturer faced significant:


A) Financial risk.
B) Promotion risk.
C) Cost estimate risk.
D) Market risk.

Correct Answer

verifed

verified

The mouse executive board meeting was drawing to a conclusion; the only way they would be able to detect the presence of the cat was to tie a bell around its tail. Under their risk management identification scheme, this would fall under:


A) Commercial risk.
B) Execution risk.
C) Financial risk.
D) Technical risk.

Correct Answer

verifed

verified

You have agreed to paint your neighbor's house a lovely shade of chartreuse for $1500 and discover much to your dismay that the house has a second floor. Now you're faced with the prospect of buying a ladder or scaffolding or a really long handled brush, not to mention the 15 more gallons of paint that will be needed to cover. You won't get another penny for what will surely be increased efforts since your neighbor transferred risk with a(n) :


A) Cost-plus contract.
B) Contingency reserve.
C) Fixed price contract.
D) Inflation clause.

Correct Answer

verifed

verified

The deliverable from the focus step of the project risk analysis and management model is:


A) A clear, unambiguous, shared understanding of all key aspects of the project documented, verified, and reported.
B) A clear, unambiguous, shared understanding of all relevant key aspects of the RMP documented, verified, and reported.
C) A clear understanding of the implications of any important simplifying assumptions about relationships between risks, responses and base plan activities.
D) Clear ownership and management allocations, effectively and efficiently defined, legally enforceable in practice where appropriate.

Correct Answer

verifed

verified

PRAM (project risk analysis and management) should be conducted as a "one-shot" activity during the project planning phase.

Correct Answer

verifed

verified

The Farm Fresh Egg project was too great for one person to pull off. The construction costs for the coop and chicken run were enormous and the sinister threat of avian flu hung over the area like a black cloud. It was only through the combined efforts of Matsushita Chickenworks and the City of Edmond that the project would be undertaken, since they would be able to:


A) Accept the risk.
B) Minimize the risk.
C) Transfer the risk.
D) Share the risk.

Correct Answer

verifed

verified

The overall consequence of failure was 0.4 and curiously enough, the consequence of performance is twice that of reliability; the consequence of reliability is twice that of schedule; and the consequence of schedule is twice that of cost. What is the consequence of failure cost?


A) 0.091
B) 0.107
C) 0.123
D) 0.136

Correct Answer

verifed

verified

To protect his poultry from meteorites, the gentleman farmer made hard hats for each bird and installed a meteor detection system that opened umbrellas throughout the yard if a meteor were detected. The safety of his flock thus assured, the farmer was surprised when he read his latest issue of Risk Management Magazine and discovered that this event was:


A) High in consequence and high in probability.
B) Low in consequence and low in probability.
C) Low in probability and high in consequence.
D) High in probability and low in consequence.

Correct Answer

verifed

verified

Sketch a 2 × 2 risk management assessment matrix and discuss the impact of each quadrant.

Correct Answer

verifed

verified

A risk management assessment matrix, as ...

View Answer

Which of these statements about the project risk analysis and management program is BEST?


A) Risk management follows a life cycle much as a project follows a life cycle.
B) The risk management strategy should be unwavering throughout the entire project life cycle.
C) If a choice between accepting and transferring risk presents itself, risk should be transferred.
D) Risk management is best handled using an ad hoc approach.

Correct Answer

verifed

verified

What are the four distinct stages of systematic risk management and what takes place at each?

Correct Answer

verifed

verified

The four distinct steps of systematic ri...

View Answer

The house had almost been framed when an F-5 tornado ripped across the plains and turned the house back into a lumber pile, albeit not stacked as neatly as it was originally. The homeowner's fears of:


A) Technical risks had come true.
B) Operating risks had come true.
C) Acts of God had come true.
D) Environmental risks had come true.

Correct Answer

verifed

verified

Each project team member had a backup that could fill in at a moment's notice should another team member fall by the wayside. The project was able to mitigate risks in this fashion thanks to an aggressive:


A) Mentoring program.
B) Cross-training program.
C) Duplication program.
D) Featherbedding program.

Correct Answer

verifed

verified

The project team toiled long into the night to develop consequence of failure scores and probability of failure scores as indicated below. What is the overall risk factor for the project? The project team toiled long into the night to develop consequence of failure scores and probability of failure scores as indicated below. What is the overall risk factor for the project?   A)  Less than or equal to 0.7 B)  Greater than 0.7 but less than or equal to 0.8 C)  Greater than 0.8 but less than or equal to 0.9 D)  Greater than 0.9


A) Less than or equal to 0.7
B) Greater than 0.7 but less than or equal to 0.8
C) Greater than 0.8 but less than or equal to 0.9
D) Greater than 0.9

Correct Answer

verifed

verified

Your project team is interested in determining an overall risk factor for your project to develop a personal submarine constructed entirely of Popsicle sticks and wood glue. Describe how you would develop reasonable estimates for each of the probability of failure categories and each of the consequence of failure categories.

Correct Answer

verifed

verified

The probability of failure categories ar...

View Answer

The risk is highest in the earliest phase of the project life cycle.

Correct Answer

verifed

verified

The European Association for Project Management has developed an integrated program of risk management based on efforts to extend risk management to cover a project's entire life cycle. This program is known as:


A) EAPM-RM.
B) RMEAPM.
C) ERM.
D) PRAM.

Correct Answer

verifed

verified

The professor wore both a belt and suspenders during lecture each day because he chose to:


A) Accept risk.
B) Minimize risk.
C) Share risk.
D) Transfer risk.

Correct Answer

verifed

verified

Showing 21 - 40 of 98

Related Exams

Show Answer