Filters
Question type

Study Flashcards

Another name for the static budget is


A) master budget.
B) overhead budget.
C) permanent budget.
D) flexible budget.

Correct Answer

verifed

verified

A static budget report


A) shows costs at only 2 or 3 different levels of activity.
B) is appropriate in evaluating a manager's effectiveness in controlling variable costs.
C) should be used when the actual level of activity is materially different from the master budget activity level.
D) may be appropriate in evaluating a manager's effectiveness in controlling costs when the behavior of the costs in response to changes in activity is fixed.

Correct Answer

verifed

verified

Dryden Manufacturing Company prepared a fixed budget of 40,000 direct labor hours, with estimated overhead costs of $200,000 for variable overhead and $60,000 for fixed overhead. Dryden then prepared a flexible budget at 38,000 labor hours. How much is total overhead costs at this level of activity?


A) $190,000
B) $250,000
C) $247,000
D) $260,000

Correct Answer

verifed

verified

Which one of the following would be the same total amount on a flexible budget and a static budget if the activity level is different for the two types of budgets?


A) Direct materials cost
B) Direct labor cost
C) Variable manufacturing overhead
D) Fixed manufacturing overhead

Correct Answer

verifed

verified

An investment center manager is considering three possible investments. The company's required return is 10%. The required asset investment, controllable margins, and the ROIs of each investment are as follows: An investment center manager is considering three possible investments. The company's required return is 10%. The required asset investment, controllable margins, and the ROIs of each investment are as follows:    The investment center is currently generating an ROI of 25% based on $1,200,000 in operating assets and a controllable margin of $300,000. Instructions If the manager can select only one project, determine which one is the best choice to increase the investment center's ROI. Compute how much the investment center's ROI will be if the manager selects your recommendation. The investment center is currently generating an ROI of 25% based on $1,200,000 in operating assets and a controllable margin of $300,000. Instructions If the manager can select only one project, determine which one is the best choice to increase the investment center's ROI. Compute how much the investment center's ROI will be if the manager selects your recommendation.

Correct Answer

verifed

verified

CC is the best choic...

View Answer

A static budget is appropriate in evaluating a manager's performance if


A) actual activity closely approximates the master budget activity.
B) actual activity is less than the master budget activity.
C) the company prepares reports on an annual basis.
D) the company is a not-for-profit organization

Correct Answer

verifed

verified

The area manager of the Little Italy Restaurants is considering two possible expansion alternatives. The required investments, expected controllable margins, and the ROIs of each are as follows: The area manager of the Little Italy Restaurants is considering two possible expansion alternatives. The required investments, expected controllable margins, and the ROIs of each are as follows:   The Little Italy segment has currently $2,000,000 in invested capital and a controllable margin of $250,000. Which one of following projects will increase the Little Italy division's ROI? A)  Both the Charlotte and Richmond options B)  Only the Charlotte option C)  Only the Richmond option D)  Neither the Charlotte nor the Richmond options The Little Italy segment has currently $2,000,000 in invested capital and a controllable margin of $250,000. Which one of following projects will increase the Little Italy division's ROI?


A) Both the Charlotte and Richmond options
B) Only the Charlotte option
C) Only the Richmond option
D) Neither the Charlotte nor the Richmond options

Correct Answer

verifed

verified

Return on investment is calculated by dividing


A) contribution margin by sales.
B) controllable margin by sales.
C) contribution margin by average operating assets.
D) controllable margin by average operating assets.

Correct Answer

verifed

verified

The activity index used in preparing the flexible budget


A) is prescribed by generally accepted accounting principles.
B) is only applicable to fixed manufacturing costs.
C) is the same for all departments.
D) should significantly influence the costs that are being budgeted.

Correct Answer

verifed

verified

A static budget is most useful for evaluating a manager's performance in controlling variable costs.

Correct Answer

verifed

verified

A static budget


A) should not be prepared in a company.
B) is useful in evaluating a manager's performance by comparing actual variable costs and planned variable costs.
C) shows planned results at the original budgeted activity level.
D) is changed only if the actual level of activity is different than originally budgeted.

Correct Answer

verifed

verified

Harbaugh Company recorded operating data for its shoe division for the year. The company's desired return is 5%. Harbaugh Company recorded operating data for its shoe division for the year. The company's desired return is 5%.   Which one of the following reflects the controllable margin for the year? A)  20% B)  50% C)  $30,000 D)  $40,000 Which one of the following reflects the controllable margin for the year?


A) 20%
B) 50%
C) $30,000
D) $40,000

Correct Answer

verifed

verified

Total budgeted fixed costs appearing on a flexible budget will be the same amount as total fixed costs on the master budget.

Correct Answer

verifed

verified

Simmons Company has two production departments, Fabricating and Assembling. At a department managers' meeting, the controller uses flexible budget graphs to explain total budgeted costs. Separate graphs based on direct labor hours are used for each department. The graphs show the following. 1. At zero direct labor hours, the total budgeted cost line and the fixed cost line intersect the vertical axis at $50,000 in the Fabricating Department, and $40,000 in the Assembling Department. 2. At normal capacity of 50,000 direct labor hours, the line drawn from the total budgeted cost line intersects the vertical axis at $180,000 in the Fabricating Department, and $145,000 in the Assembling Department. Instructions (a) State the total budgeted cost formula for each department. (b) Compute the total budgeted cost for each department, assuming actual direct labor hours worked were 53,000 and 47,000, in the Fabricating and Assembling Departments, respectively.

Correct Answer

verifed

verified

(a) Fabricating Department = $50,000 fix...

View Answer

Budget reports provide the feedback needed by management to see whether actual operations are on course.

Correct Answer

verifed

verified

What budgeted amounts appear on the flexible budget?


A) Original budgeted amounts at the static budget activity level
B) Actual costs for the budgeted activity level
C) Budgeted amounts for the actual activity level achieved
D) Actual costs for the estimated activity level

Correct Answer

verifed

verified

Rob Haughton is the North Division manager and his performance is evaluated by executive management based on Division ROI. The current controllable margin for North Division is $46,000. Its current operating assets total $210,000. The division is considering purchasing equipment for $40,000 that will increase sales by an estimated $10,000, with annual depreciation of $10,000. If the equipment is purchased, what will happen to the return on investment for the division?


A) An increase of 0.5%
B) A decrease of 0.5%
C) A decrease of 3.5%
D) It will remain unchanged.

Correct Answer

verifed

verified

Data for the Electric Division of Nordmeyer Company which is operated as an investment center follows: Data for the Electric Division of Nordmeyer Company which is operated as an investment center follows:    Instructions Calculate controllable margin and average operating assets. Instructions Calculate controllable margin and average operating assets.

Correct Answer

verifed

verified

Controllable Margin ($800,000 ...

View Answer

A flexible budget graph for the Assembly Department shows the following: 1. At zero direct labor hours, the total budgeted cost line intersects the vertical axis at $60,000. 2. At normal capacity of 50,000 direct labor hours, the line drawn from the total budgeted cost line intersects the vertical axis at $180,000. Instructions Develop the budgeted cost formula for the Assembly Department and identify the fixed and variable costs.

Correct Answer

verifed

verified

Management by exception means that management will investigate areas where actual results differ from planned results if the items are material and controllable.

Correct Answer

verifed

verified

Showing 61 - 80 of 207

Related Exams

Show Answer