A) master budget.
B) overhead budget.
C) permanent budget.
D) flexible budget.
Correct Answer
verified
Multiple Choice
A) shows costs at only 2 or 3 different levels of activity.
B) is appropriate in evaluating a manager's effectiveness in controlling variable costs.
C) should be used when the actual level of activity is materially different from the master budget activity level.
D) may be appropriate in evaluating a manager's effectiveness in controlling costs when the behavior of the costs in response to changes in activity is fixed.
Correct Answer
verified
Multiple Choice
A) $190,000
B) $250,000
C) $247,000
D) $260,000
Correct Answer
verified
Multiple Choice
A) Direct materials cost
B) Direct labor cost
C) Variable manufacturing overhead
D) Fixed manufacturing overhead
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) actual activity closely approximates the master budget activity.
B) actual activity is less than the master budget activity.
C) the company prepares reports on an annual basis.
D) the company is a not-for-profit organization
Correct Answer
verified
Multiple Choice
A) Both the Charlotte and Richmond options
B) Only the Charlotte option
C) Only the Richmond option
D) Neither the Charlotte nor the Richmond options
Correct Answer
verified
Multiple Choice
A) contribution margin by sales.
B) controllable margin by sales.
C) contribution margin by average operating assets.
D) controllable margin by average operating assets.
Correct Answer
verified
Multiple Choice
A) is prescribed by generally accepted accounting principles.
B) is only applicable to fixed manufacturing costs.
C) is the same for all departments.
D) should significantly influence the costs that are being budgeted.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) should not be prepared in a company.
B) is useful in evaluating a manager's performance by comparing actual variable costs and planned variable costs.
C) shows planned results at the original budgeted activity level.
D) is changed only if the actual level of activity is different than originally budgeted.
Correct Answer
verified
Multiple Choice
A) 20%
B) 50%
C) $30,000
D) $40,000
Correct Answer
verified
True/False
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) Original budgeted amounts at the static budget activity level
B) Actual costs for the budgeted activity level
C) Budgeted amounts for the actual activity level achieved
D) Actual costs for the estimated activity level
Correct Answer
verified
Multiple Choice
A) An increase of 0.5%
B) A decrease of 0.5%
C) A decrease of 3.5%
D) It will remain unchanged.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Essay
Correct Answer
verified
True/False
Correct Answer
verified
Showing 61 - 80 of 207
Related Exams