Filters
Question type

Study Flashcards

You should replace a machine when the EAC of continuing to operate it exceeds the EAC of the new machine.

Correct Answer

verifed

verified

Briefly explain the acronym MACRS.

Correct Answer

verifed

verified

MACRS is short for Modified Accelerated ...

View Answer

The cost of a resource that may be relevant to an investment decision even when no cash changes hand is called a (an) :


A) Sunk cost
B) Opportunity cost
C) Working capital
D) None of the above

Correct Answer

verifed

verified

Opportunity costs should not be included as they are missed opportunities.

Correct Answer

verifed

verified

Briefly explain how the cost of excess capacity is taken into consideration.

Correct Answer

verifed

verified

Many managers assume that the marginal c...

View Answer

You have been asked to evaluate a project with infinite life. Sales and costs are projected to be $1000 and $500 respectively. There is no depreciation and the tax rate is 30%. The real required rate of return is 10%. The inflation rate is 4% and is expected to be 4% forever. Sales and costs will increase at the rate of inflation. If the project costs $3000, what is the NPV?


A) $500.00
B) $1629.62
C) $365.38
D) None of the above

Correct Answer

verifed

verified

Real cash flow occurring in year-2 is $60,000. If the inflation rate is 5% per year, the real rate of interest is 2%, calculate the cash flow for the year-2.


A) $60,000
B) $55,422
C) $66,150
D) None of the above

Correct Answer

verifed

verified

Investment in net working capital is not depreciated because:


A) It is not a cash flow
B) It is recovered during or at the end of the project and is not a depreciating asset
C) It is a sunk cost
D) All of the above

Correct Answer

verifed

verified

Which of the following countries allow firms to keep two separate sets of books, one for the stockholders and one for the tax authorities like the Internal Revenue Service? I. U.S.A II) Japan III) France


A) I only
B) I and II only
C) I, II, and III only
D) None of the above

Correct Answer

verifed

verified

By undertaking the analysis in real terms, the financial manager avoids having to forecast inflation.

Correct Answer

verifed

verified

A capital equipment costing $400,000 today has no (zero) salvage value at the end of 5 years. If straight-line depreciation is used, what is the book value of the equipment at the end of three years?


A) $120,000
B) $80,000
C) $160,000
D) $240,000

Correct Answer

verifed

verified

If the nominal interest rate is 7. 5% and the inflation rate is 4%, what is the real interest rate?


A) 4%
B) 9.5%
C) 3.4%
D) None of the above

Correct Answer

verifed

verified

If the discount rate is stated in nominal terms, then in order to calculate the NPV in a consistent manner requires that project: I. cash flows be estimated in nominal terms II. cash flows be estimated in real terms III. accounting income be used


A) I only
B) II only
C) III only
D) None of the above

Correct Answer

verifed

verified

When calculating cash flows, it is important to consider all incidental effects.

Correct Answer

verifed

verified

When evaluating a projects with positive NPV but variable life spans, the proper technique to employ is the equivalent annual annuity (EAA) approach.

Correct Answer

verifed

verified

Depreciation acts as a tax shield in reducing the taxes.

Correct Answer

verifed

verified

The real rate of interest is 3% and the inflation is 4%. What is the nominal rate of interest?


A) 3%
B) 4%
C) 7.12%
D) 1%

Correct Answer

verifed

verified

The rule for comparing machines with different lines is to select the machine with the greatest equivalent annual cost (EAC).

Correct Answer

verifed

verified

How do you compare projects with different lives?

Correct Answer

verifed

verified

Projects with different lives are compar...

View Answer

Given the following data for Project M: \begin{array}{c}\begin{array}{lll}\\\text {Cash flow in real terms:}\\\text {Real discount rate =\mathbf{5} \% }\\\text {Nominal discount rate \( =10 \% \) }\\\text {Calculate the NPV of the project}\end{array}\begin{array}{lll}C_{0} & C_{1} & C_{2} \\-200 & 150 & 120\\\\\\\\\end{array}\end{array}


A) $51.70
B) $35.54
C) $45.21
D) None of the above

Correct Answer

verifed

verified

Showing 21 - 40 of 72

Related Exams

Show Answer