Filters
Question type

One thing that an MRP II system has that an MRP system does not is ________.

Correct Answer

verifed

verified

a linkage ...

View Answer

Dependent demand for an item occurs because the quantity required for it varies with the production plans of one or more parents.

Correct Answer

verifed

verified

True

Scenario 11.2 Scenario 11.2         Inventory amounts indicated in the table are available to produce the end item indicated in this bill of materials. -Use Scenario 11.2 to answer this question. How many additional units of F are needed to produce twelve end items? A)  174 B)  192 C)  182 D)  160 Scenario 11.2         Inventory amounts indicated in the table are available to produce the end item indicated in this bill of materials. -Use Scenario 11.2 to answer this question. How many additional units of F are needed to produce twelve end items? A)  174 B)  192 C)  182 D)  160 Inventory amounts indicated in the table are available to produce the end item indicated in this bill of materials. -Use Scenario 11.2 to answer this question. How many additional units of F are needed to produce twelve end items?


A) 174
B) 192
C) 182
D) 160

Correct Answer

verifed

verified

The L4L rule is a special case of the ________.

Correct Answer

verifed

verified

POQ rule

Which one of the following is a feature of MRP II, but not available in basic MRP systems?


A) financial projections
B) action notices
C) dispatch lists
D) capacity reporting

Correct Answer

verifed

verified

A

Consider the MPS, BOM, and inventory data shown. Master Production Schedule: The following table shows the MPS start quantities for the next 10 weeks. Consider the MPS, BOM, and inventory data shown. Master Production Schedule: The following table shows the MPS start quantities for the next 10 weeks.     Bill of Material: - Item A uses 2 each of component D, 1 each of component C and 2 each of subassembly B. - Subassembly B uses 2 each of component E. Selected Inventory Data:     Construct the MRP schedule using the preceding information. Bill of Material: - Item A uses 2 each of component D, 1 each of component C and 2 each of subassembly B. - Subassembly B uses 2 each of component E. Selected Inventory Data: Consider the MPS, BOM, and inventory data shown. Master Production Schedule: The following table shows the MPS start quantities for the next 10 weeks.     Bill of Material: - Item A uses 2 each of component D, 1 each of component C and 2 each of subassembly B. - Subassembly B uses 2 each of component E. Selected Inventory Data:     Construct the MRP schedule using the preceding information. Construct the MRP schedule using the preceding information.

Correct Answer

verifed

verified

Explain why, in a dependent demand environment, MRP does a better job of estimating the need to replenish inventory items than does the reorder point system.

Correct Answer

verifed

verified

MRP works better for dependent-demand en...

View Answer

How can an MRP system be used in a firm's sustainability efforts?

Correct Answer

verifed

verified

Companies can modify their MRP systems t...

View Answer

Use the bill of materials and inventory records to determine the additional quantities of purchased items necessary to assemble 20 end items if the manufacturer uses lot-for-lot ordering. There are no end items currently on hand, and none of the components have any scheduled receipts. Use the bill of materials and inventory records to determine the additional quantities of purchased items necessary to assemble 20 end items if the manufacturer uses lot-for-lot ordering. There are no end items currently on hand, and none of the components have any scheduled receipts.         Inventory amounts indicated in the table are available to produce the end item indicated in this bill of materials. Use the bill of materials and inventory records to determine the additional quantities of purchased items necessary to assemble 20 end items if the manufacturer uses lot-for-lot ordering. There are no end items currently on hand, and none of the components have any scheduled receipts.         Inventory amounts indicated in the table are available to produce the end item indicated in this bill of materials. Inventory amounts indicated in the table are available to produce the end item indicated in this bill of materials.

Correct Answer

verifed

verified

Planned receipts are estimates of the amount of inventory available each week after gross requirements have been satisfied.

Correct Answer

verifed

verified

The companies SAP AG and Microsoft have the largest installed base of customers for ERP packages.

Correct Answer

verifed

verified

Which of the following is not used to derive an item's gross requirements?


A) the MPS for immediate parents that are end items
B) the planned order releases for immediate parents below the MPS level
C) the MPS components that are not purchased items
D) any other requirements not originating in the MPS, such as the demand for replacement parts

Correct Answer

verifed

verified

Part commonality tends to increase inventory costs.

Correct Answer

verifed

verified

Waiting time and process time are two components of ________.

Correct Answer

verifed

verified

An ERP system revolves around a single comprehensive database that is made available across the entire organization.

Correct Answer

verifed

verified

Under which one of the following circumstances can an MRP system be used to its best advantage?


A) when the item's demand depends only on customer demand
B) when the item's demand is uniform
C) when the item's demand is constant
D) when the item's demand depends on the production plans of its parent(s)

Correct Answer

verifed

verified

The sums of the quantities in the master production schedule must equal those in the ________.

Correct Answer

verifed

verified

sales and ...

View Answer

Which one of the following statements about lot-sizing rules is True?


A) The periodic order quantity (POQ) rule seeks to create inventory remnants.
B) If the POQ rule is used, an item's lot size can vary each time an order is placed.
C) The lot-for-lot (L4L) rule is a special case of the fixed-order quantity (FOQ) rule.
D) All lot-sizing rules seek to minimize inventory levels.

Correct Answer

verifed

verified

Scenario 11.3 Use this bill of materials and inventory records to answer the questions. Scenario 11.3 Use this bill of materials and inventory records to answer the questions.        -Use Scenario 11.3 to answer this question. How many additional units of N are required to produce 25 end items? A)  138 B)  150 C)  124 D)  112 Scenario 11.3 Use this bill of materials and inventory records to answer the questions.        -Use Scenario 11.3 to answer this question. How many additional units of N are required to produce 25 end items? A)  138 B)  150 C)  124 D)  112 -Use Scenario 11.3 to answer this question. How many additional units of N are required to produce 25 end items?


A) 138
B) 150
C) 124
D) 112

Correct Answer

verifed

verified

The portion of the master production schedule farthest into the future is often frozen to reduce forecasting requirements.

Correct Answer

verifed

verified

Showing 1 - 20 of 124

Related Exams

Show Answer