In a resource-constrained project the second priority in assigning resources is usually given to activities with the


A) smallest duration.
B) least slack.
C) most slack.
D) lowest identification number.
E) highest cost.

Correct Answer

verifed

verified

When leveling schedules to overcome resource constraints, ___________ is increased.


A) impact of risks
B) scheduling complexity
C) cost
D) amount of total slack
E) amount of free slack

Correct Answer

verifed

verified

Renovation of a small compartment in a houseboat or camping trailer that is too small for more than one person is an example of a(n) ________ resource constraint.


A) physical
B) people
C) material
D) equipment
E) budget

Correct Answer

verifed

verified

While balancing assignments, a project manager must also balance:


A) Overall project cost.
B) Talent development.
C) Earned value.
D) Work package slack.
E) Project cost.

Correct Answer

verifed

verified

B

If a project needs one earth mover six months from now in order to complete one activity, and the organization has four such machines, there is no equipment resource constraint.

Correct Answer

verifed

verified

When using resource-constrained scheduling, activities that were once scheduled to be completed at the same time now may have to be scheduled in sequence. What are the "rules of thumb" or heuristics that need to be followed to determine which activity is scheduled first?

Correct Answer

verifed

verified

The first priority is to allocate resour...

View Answer

When resource constraints are added to technical constraints the original project network may change as well as the completion date.

Correct Answer

verifed

verified

Resource bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules.

Correct Answer

verifed

verified

True

In reviewing the status of a project with top management, a team leader was told that there are only two programmers that can be used for the project. The project is classified as __________ constrained.


A) time
B) quality
C) cost
D) performance
E) resource

Correct Answer

verifed

verified

In reality resource allocation generally occurs in a(n) ___________ environment where the demands of one project have to be reconciled with the needs of other projects.


A) uncertain
B) multiproject
C) budget-constrained
D) risky
E) controlled

Correct Answer

verifed

verified

Delaying noncritical activities to lower peak demand and, thus, increase resource utilization is called resource __________.


A) smoothing
B) slack utilization
C) switching
D) re-scheduling
E) overtime

Correct Answer

verifed

verified

All resource leveling techniques involve


A) delaying noncritical activities.
B) delaying critical activities.
C) using negative slack.
D) delaying the project.
E) adding resources.

Correct Answer

verifed

verified

Which of the following is NOT one of the more common problems associated with scheduling multi-project resources?


A) Overall schedule slippage
B) Inefficient resource utilization
C) Decline in project quality
D) Resource bottlenecks
E) Delays in one project causing delays in other projects

Correct Answer

verifed

verified

All leveling techniques delay noncritical activities by using positive slack to smooth out the resource requirements.

Correct Answer

verifed

verified

Since resource leveling or smoothing delays noncritical activities, a common result is a decrease in network sensitivity.

Correct Answer

verifed

verified

When developing a new software package, logically, the software must be designed before the code is written, and the code must be written before it is tested. These activities are dependent on each other by _________ constraints.


A) physical
B) technical
C) resource
D) schedule
E) time

Correct Answer

verifed

verified

Resource leveling or smoothing is only used on projects which are resource constrained.

Correct Answer

verifed

verified

Splitting is a scheduling technique used to get a better schedule or better resource utilization and should be used without hesitation.

Correct Answer

verifed

verified

All of the following are benefits of scheduling resources before project implementation EXCEPT


A) it allows time for considering reasonable options if resource constraints do exist.
B) the project completion date can be established.
C) work packages can be time-phased.
D) it allows managers to share resources with other project managers if it is requested without negatively impacting their project.
E) it ensures low network sensitivity.

Correct Answer

verifed

verified

Resource constraints can be overcome by creative and efficient scheduling.

Correct Answer

verifed

verified

False