Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) actual cost.
B) realized risks.
C) planned value.
D) Both actual cost and planned value.
E) All of these alternatives are correct.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) review the baseline plan with top management.
B) analyze inputs to control system.
C) compare plan against actual.
D) measure progress and performance.
E) review spending with team members.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Suppliers
B) Equipment
C) Labor
D) Budget reserves
E) Contractors
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) under cost or behind schedule.
B) over cost or ahead of schedule.
C) under cost or ahead of schedule.
D) over cost or behind schedule.
E) on cost or on schedule.
Correct Answer
verified
Multiple Choice
A) CPI
B) EV
C) CV
D) SV
E) EAC
Correct Answer
verified
Multiple Choice
A) SV / CV
B) EV / PV
C) EV / AC
D) AC / SV
E) AC / CV
Correct Answer
verified
Multiple Choice
A) EV − AC
B) AC − SV
C) PV − EV
D) CV − EV
E) EV − PV
Correct Answer
verified
Multiple Choice
A) estimated completion
B) estimated cost
C) percent complete
D) estimation
E) estimation method
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) project cost to date adjusted for project scope changes.
B) total project cost to date.
C) cost incurred minus the planned cost.
D) percent of the original budget that has been earned by work that is completed.
E) the planned time-phased baseline of the value of work scheduled.
Correct Answer
verified
Showing 41 - 60 of 98
Related Exams