Filters
Question type

Study Flashcards

What is the percent complete rule and what role does it play when developing an earned value cost / schedule system?

Correct Answer

verifed

verified

The percent complete rule is used when s...

View Answer

A common project practice is to ignore straight labor hours when calculating earned value.

Correct Answer

verifed

verified

When reviewing the cost variance on a project, you compare Earned Value with


A) actual cost.
B) realized risks.
C) planned value.
D) Both actual cost and planned value.
E) All of these alternatives are correct.

Correct Answer

verifed

verified

What is the difference between a baseline Gantt chart and a tracking Gantt chart?

Correct Answer

verifed

verified

The baseline chart is created during the...

View Answer

The second step in the project control process for measuring and evaluating project performance is to


A) review the baseline plan with top management.
B) analyze inputs to control system.
C) compare plan against actual.
D) measure progress and performance.
E) review spending with team members.

Correct Answer

verifed

verified

A positive VAC indicates that the project will be completed under budget.

Correct Answer

verifed

verified

Baseline costs typically include labor, equipment, materials and direct overhead cost.

Correct Answer

verifed

verified

Most changes will not result in serious scope changes and should be absorbed as positive or negative variances.

Correct Answer

verifed

verified

Of the following costs, which are NOT included in baseline?


A) Suppliers
B) Equipment
C) Labor
D) Budget reserves
E) Contractors

Correct Answer

verifed

verified

In reviewing the budget report of a project, you notice that spending on the project is running about 10 percent over plan. Is the project in trouble? Support your answer.

Correct Answer

verifed

verified

You don't know for sure. The project may...

View Answer

A CPI or SPI value less than one indicates that the project is currently


A) under cost or behind schedule.
B) over cost or ahead of schedule.
C) under cost or ahead of schedule.
D) over cost or behind schedule.
E) on cost or on schedule.

Correct Answer

verifed

verified

Which performance index is the most potentially misleading?


A) CPI
B) EV
C) CV
D) SV
E) EAC

Correct Answer

verifed

verified

Which of the following methods will measure the scheduling efficiency of the work accomplished to date?


A) SV / CV
B) EV / PV
C) EV / AC
D) AC / SV
E) AC / CV

Correct Answer

verifed

verified

The schedule variance for a project is calculated by:


A) EV − AC
B) AC − SV
C) PV − EV
D) CV − EV
E) EV − PV

Correct Answer

verifed

verified

When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the ____________ rule.


A) estimated completion
B) estimated cost
C) percent complete
D) estimation
E) estimation method

Correct Answer

verifed

verified

Schedule variance (SV) is in dollars and does not directly represent time. Why is it still useful?

Correct Answer

verifed

verified

Schedule variance presents an overall as...

View Answer

Earned value is defined as the budgeted cost of the actual work performed.

Correct Answer

verifed

verified

Two project complete indexes are used, depending on your judgment of which one is most representative of your project. Identify both indexes and explain when it is most appropriate to use each.

Correct Answer

verifed

verified

The PCIB assumes the original budget of ...

View Answer

The best method for assigning costs to the baseline under the 50 / 50 rule is to establish frequent checkpoints over the duration of the work package and assign completion percentages in dollar terms.

Correct Answer

verifed

verified

The earned value of a project is the


A) project cost to date adjusted for project scope changes.
B) total project cost to date.
C) cost incurred minus the planned cost.
D) percent of the original budget that has been earned by work that is completed.
E) the planned time-phased baseline of the value of work scheduled.

Correct Answer

verifed

verified

Showing 41 - 60 of 98

Related Exams

Show Answer