A) are not on the critical path.
B) are the least costly to crash.
C) are costly to crash and are on the critical path.
D) are on the critical path and are the least costly to crash.
E) are the easiest to crash.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) .5000
B) .8413
C) .9544
D) .9772
E) .9987
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 14
B) 15
C) 16
D) 17
E) 18
Correct Answer
verified
Multiple Choice
A) 13.
B) 15.
C) 20.
D) 52.
E) 81.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) early in; most costly
B) late in; least costly
C) late in; most costly
D) before the beginning of; most complex
E) at the conclusion of; least complex
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 35 weeks
B) 39 weeks
C) 50 weeks
D) 104 weeks
E) 105 weeks
Correct Answer
verified
Multiple Choice
A) it imposes a methodology and a common project management terminology.
B) it provides a logical planning structure.
C) it can enhance communication among team members.
D) it enables what-if scenarios.
E) it can fix the occurrence of constraint violations.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 100 days
B) 140 days
C) 199 days
D) 200 days
E) 440 days
Correct Answer
verified
Multiple Choice
A) II; IV
B) III; IV
C) I; III
D) I; II
E) II; III
Correct Answer
verified
Multiple Choice
A) direct costs.
B) performance.
C) quality.
D) conflict.
E) duration.
Correct Answer
verified
Multiple Choice
A) 0 days
B) 20 days
C) 40 days
D) 60 days
E) 100 days
Correct Answer
verified
Multiple Choice
A) planning and constructing a new city hall
B) developing an advertising campaign for a new product
C) designing and constructing a subway system
D) writing a poem
E) preparing for the visit of a foreign dignitary
Correct Answer
verified
Multiple Choice
A) deciding which projects to implement
B) selecting the project manager
C) selecting the project team
D) planning and designing the project
E) managing and controlling project resources
Correct Answer
verified
Multiple Choice
A) 2 days
B) 3 days
C) 4 days
D) 16 days
E) 24 days
Correct Answer
verified
Showing 41 - 60 of 118
Related Exams