Filters
Question type

Study Flashcards

What is the probability that the critical path for this project will be completed within 210 days?


A) 0.5000
B) 0.8413
C) 0.9544
D) 0.9772
E) 0.9987

Correct Answer

verifed

verified

An advantage of Gantt charts in project management is that they reveal which activities can be delayed without delaying the overall project.

Correct Answer

verifed

verified

What is the estimated expected (mean) duration for project completion?


A) 160 days
B) 170 days
C) 200 days
D) 210 days
E) 300 days

Correct Answer

verifed

verified

Activity 7 is directly preceded by two activities-activity 5 and activity 6.Activity 5 has an expected duration of five and an ES time of six.Activity 6 has an expected duration of seven and an ES time of seven.Activity 7 has an expected duration of 10.The ES for activity 7 is:


A) 11
B) 14
C) 21
D) 24
E) 25

Correct Answer

verifed

verified

  -What is the estimated expected (mean)duration (in weeks)for project completion? -What is the estimated expected (mean)duration (in weeks)for project completion?

Correct Answer

verifed

verified

  -What are the estimated slack times (in weeks)for activities A-H? -What are the estimated slack times (in weeks)for activities A-H?

Correct Answer

verifed

verified

0; 5; 15; ...

View Answer

In a precedence network the critical path is the sequence of activities which has:


A) the most activities.
B) the most nodes.
C) the most events.
D) the longest duration.
E) the greatest variance.

Correct Answer

verifed

verified

What is the estimated expected (mean) duration for project completion?


A) 100 days
B) 140 days
C) 199 days
D) 200 days
E) 440 days

Correct Answer

verifed

verified

  -What is the estimated standard deviation (in weeks)for the critical path completion time? -What is the estimated standard deviation (in weeks)for the critical path completion time?

Correct Answer

verifed

verified

Following project initiation,planning and scheduling,project execution is the last phase of a projects life cycle.

Correct Answer

verifed

verified

Which of the following are advantages of CPM/PERT? I.Relationships among activities can be identified. II.Slippage in project activities is no longer an issue. III.Activities that need to be watched closely can be identified.


A) I and II
B) II and III
C) III only
D) I and III
E) I, II, and III

Correct Answer

verifed

verified

A project consists of nine major activities,as shown.There are three separate paths in the network: a-c-f,b-d-g,and e-h-i. (i)What is expected project duration time? (ii)Determine the probability that the project will take more than 35 weeks to complete.(All durations are in weeks.) A project consists of nine major activities,as shown.There are three separate paths in the network:  a-c-f,b-d-g,and e-h-i. (i)What is expected project duration time? (ii)Determine the probability that the project will take more than 35 weeks to complete.(All durations are in weeks.)

Correct Answer

verifed

verified

blured image (i)32 wk.
(ii)P(Pro...

View Answer

Careful planning of complex projects can eliminate the occurrence of risk events that have undesirable consequences.

Correct Answer

verifed

verified

  -What activities make up the critical path? -What activities make up the critical path?

Correct Answer

verifed

verified

Critical p...

View Answer

  -What is the probability that the critical path for this project will be completed within 75 weeks?  80 weeks?  85 weeks?  90 weeks? -What is the probability that the critical path for this project will be completed within 75 weeks? 80 weeks? 85 weeks? 90 weeks?

Correct Answer

verifed

verified

.5; .8413;...

View Answer

What is the estimated slack time for Activity E?


A) 0 weeks
B) 3 weeks
C) 9 weeks
D) 11 weeks
E) 12 weeks

Correct Answer

verifed

verified

Which of the following is not an advantage of using project management software?


A) It automatically generates and formats a variety of reports.
B) It reduces project costs.
C) It can enhance communication among team members.
D) It can generate various charts.
E) It provides a logical planning structure.

Correct Answer

verifed

verified

The probability that the project will go beyond the desired time is equal to one minus the joint probability that all paths will be completed within the desired time.

Correct Answer

verifed

verified

Given the network diagram above,determine each of the following: (i)the activities which are on the critical path (ii)the expected project duration (iii)the probability that the project will be completed in 29 weeks or less (Note: the numbers on each node refers to the expected duration and standard deviation in weeks for that activity. E.G., 8,2 indicates an expected duration of eight and a standard deviation of two weeks.) Given the network diagram above,determine each of the following: (i)the activities which are on the critical path (ii)the expected project duration (iii)the probability that the project will be completed in 29 weeks or less (Note:  the numbers on each node refers to the expected duration and standard deviation in weeks for that activity. E.G., 8,2 indicates an expected duration of eight and a standard deviation of two weeks.)

Correct Answer

verifed

verified

blured image (i)The critical path is C-E-H.
(ii)Expe...

View Answer

The expected duration of this project is:


A) 12
B) 17
C) 20
D) 36
E) 77

Correct Answer

verifed

verified

Showing 81 - 100 of 127

Related Exams

Show Answer