If your project has spent $50,000 versus a budget of $45,000 and it is a week ahead of schedule,is it a certainty that your project is doing well? Explain why or why not.

Correct Answer

verifed

verified

Rachel is working on a project that technically allows three activities to be done at the same time.If they were to be implemented at the same time,she would need 5 contractors in order for the activities to be completed on time.There are only 3 available for her to use.This is an example of what type of constraint?


A) Technical
B) People
C) Equipment
D) Physical
E) Materials

Correct Answer

verifed

verified

All resource leveling techniques involve


A) Delaying noncritical activities.
B) Delaying critical activities.
C) Using negative slack.
D) Delaying the project.
E) Adding resources.

Correct Answer

verifed

verified

When scheduling activities in a resource-constrained project typically the activity scheduled first has the most amount of slack.

Correct Answer

verifed

verified

Why should project managers be cautious about using the splitting scheduling technique?

Correct Answer

verifed

verified

Resources are adequate,but demand varies widely over the life of the project.Delaying noncritical activities to lower peak demand on resources is known as resource


A) Shifting.
B) Effectiveness.
C) Manipulating.
D) Smoothing.
E) Allocation.

Correct Answer

verifed

verified

Resource bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules.

Correct Answer

verifed

verified

In a resource-constrained project,the completion date is most likely to change.

Correct Answer

verifed

verified

Having one person responsible for performing several activities,all due at the same time,is an example of a(n)________ constraint.

Correct Answer

verifed

verified

resource
Explanation: If one p...

View Answer

Identify and give an example of the three types of resource constraints.

Correct Answer

verifed

verified

Gene is trying to order the concrete needed to continue his project.However,the supplier will not be able to deliver it until next week.This is an example of what kind of resource constraint?


A) Working capital
B) People
C) Equipment
D) Information
E) Materials

Correct Answer

verifed

verified

Tony has realized that two activities in his project cannot be done at the same time because not enough resources are available.Activity 3 is critical and has a duration of 5 days.Activity 4 has 2 days of slack and a duration of 2 days.How will he decide which activity should be scheduled first?


A) The activity with the smallest duration
B) The activity with the least slack
C) The activity with the most slack
D) The activity with the lowest identification number
E) The activity with the highest cost

Correct Answer

verifed

verified

After resource leveling or smoothing one goal is that the amount of resources needed over the life of the project will be ___________.

Correct Answer

verifed

verified

reduced
Explanation: The three goals of ...

View Answer

Splitting is a scheduling technique used to get a better schedule or better resource utilization and should be used without hesitation.

Correct Answer

verifed

verified

A special truck that George needs on his project has been scheduled on another project.This is an example of what type of resource constraint?


A) Working capital
B) People
C) Equipment
D) Information
E) Materials

Correct Answer

verifed

verified

All of the following are benefits of scheduling resources before project implementation EXCEPT


A) It allows time for considering reasonable options if resource constraints do exist.
B) The project completion date can be established.
C) Work packages can be time-phased.
D) It allows managers to share resources with other project managers if it is requested without negatively impacting their project.
E) It ensures low network sensitivity.

Correct Answer

verifed

verified

Resource leveling or smoothing can have all the following results on a project EXCEPT


A) Lower peak resource demand.
B) Reduced resource need over the life of the project.
C) Reduced fluctuations in resource demand.
D) A longer project duration.
E) A more sensitive network.

Correct Answer

verifed

verified

Many companies are ________ project work to contractors and consultants as a means of dealing with the peaks and valleys of resource allocation among projects.

Correct Answer

verifed

verified

outsourcing
Explanation: Many companies ...

View Answer

Without a time-phased budget a good project schedule and cost control are impossible.

Correct Answer

verifed

verified

When a project is classified as resource-constrained and a resource constraint exists,the project duration is typically __________.

Correct Answer

verifed

verified

extended
Explanation: If resources are n...