The schedule variance for a project is calculated by:


A) EV - AC
B) AC - SV
C) PV - EV
D) CV - EV
E) EV - PV

Correct Answer

verifed

verified

A common project practice is to ignore straight labor hours when calculating Earned Value.

Correct Answer

verifed

verified

Schedule variance (SV)is in dollars and does not directly represent time.Why is it still useful?

Correct Answer

verifed

verified

Schedule variance presents an overall as...

View Answer

What is scope creep and how does it impact project control?

Correct Answer

verifed

verified

Scope creep is small refinements that ev...

View Answer

Deciding what data to collect, actually collecting the data and analyzing it, and reporting this data are all parts of structuring a project monitoring information system.

Correct Answer

verifed

verified

Which of the following methods of variance analysis is the best indicator of how far off the budget a project will be at completion?


A) BAC
B) EAC
C) ETC
D) VAC
E) TCPI

Correct Answer

verifed

verified

All projects need some form of formal control.Agree or disagree? Support you answer.

Correct Answer

verifed

verified

Control by "wandering around" and/or "in...

View Answer

The _________ index measures the project percent complete in relation to the resources that were budgeted.

Correct Answer

verifed

verified

PCIB
Explanation: The PCIB ind...

View Answer

When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the ____________ rule.

Correct Answer

verifed

verified

percent complete
Explanation: The percen...

View Answer

Most changes will not result in serious scope changes and should be absorbed as positive or negative variances.

Correct Answer

verifed

verified

Which of the following are required to assess the current status of a project using the earned-value cost/schedule system?


A) BAC, EAC, and ETC
B) VAC, EAC, and BAC
C) CV, SV, and BAC
D) PV, EV, and AC
E) TCPI, EV, and PV

Correct Answer

verifed

verified

When revising the estimated cost at completion, there are two approaches.The EACre is determined by experts in the field and the EACf is a mathematical approach which assumes the CPI as the basis for forecasting cost at completion.

Correct Answer

verifed

verified

Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for each $1 worth of scheduled work.Nancy got this information from viewing the


A) SV.
B) TCPI.
C) CPI.
D) SPI.
E) PCIB.

Correct Answer

verifed

verified

The start of a task may be moved on a Tracking Gantt due to


A) Increase in Earned Value.
B) Lack of an update Control Chart.
C) A predecessor task starting late.
D) Increase in Earned Value and Lack of an update Control Chart.

Correct Answer

verifed

verified

Schedule variance measures progress in time units.

Correct Answer

verifed

verified

The first step in the project control process for measuring and evaluating project performance is to


A) Set a baseline plan.
B) Determine the project objectives.
C) Determine the project deliverables.
D) Analyze the project budget.
E) Review the project priority matrix.

Correct Answer

verifed

verified

A project control system allows for comparing actual performance against plan to identify deviations; however, the system doesn't impact the quality of communication between stakeholders.

Correct Answer

verifed

verified

If the cost of labor and materials has not been separated there is additional analysis required to determine the cause of the calculated variance.

Correct Answer

verifed

verified

What is the percent complete rule and what role does it play when developing an earned value cost/schedule system?

Correct Answer

verifed

verified

The percent complete rule is used when s...

View Answer

Sally receives the following information on her project: PV = 100, AC = 75, EV = 100.How well is the project doing in terms of budget?


A) Right on budget
B) 25 under budget
C) 25 over budget
D) 50 under budget
E) 50 over budget

Correct Answer

verifed

verified