A) The inherent risk associated with the activity
B) How crashing will impact the morale and motivation of the individuals working on that activity
C) Resource availability after crashing that activity
D) The level of difficulty involved in completing the activity
E) When during the project the activity will occur
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
Short Answer
Correct Answer
verified
View Answer
Multiple Choice
A) Reduce project scope
B) Have owner take more responsibility
C) Move the completion date further out
D) Brainstorm cost savings options
E) Outsource project activities
Correct Answer
verified
Multiple Choice
A) Assign additional staff and equipment
B) Establish a core team
C) Do it twice-first fast and then correctly
D) Reduce project scope
E) Compromise quality
Correct Answer
verified
Multiple Choice
A) Normal
B) Budgeted
C) Optimized
D) Expected
E) Targeted
Correct Answer
verified
Multiple Choice
A) Involves crashing all activities to their crash point.
B) Can only be done when resources are not constrained.
C) Is always more expensive.
D) Tends to increase network sensitivity.
E) Should be considered for all projects.
Correct Answer
verified
Multiple Choice
A) Expedited
B) Accelerated
C) Crash
D) Optimistic
E) Optimal
Correct Answer
verified
Multiple Choice
A) Labor, material and equipment costs.
B) Direct costs plus interest.
C) Direct labor costs and the project manager's salary.
D) Direct costs and the project manager's salary.
E) Direct and indirect costs.
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
Short Answer
Correct Answer
verified
View Answer
Essay
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Short Answer
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
Showing 1 - 20 of 106
Related Exams