When determining which activity to crash, there are other factors that should be assessed beyond cost.Which of the following is NOT one of these factors?


A) The inherent risk associated with the activity
B) How crashing will impact the morale and motivation of the individuals working on that activity
C) Resource availability after crashing that activity
D) The level of difficulty involved in completing the activity
E) When during the project the activity will occur

Correct Answer

verifed

verified

Without any formal planning, the president of a software company remarks in a speech that new technologically advanced software will be available in one year.This may lead to a project that must be done faster than anticipated.The completion date has been __________.

Correct Answer

verifed

verified

imposed
Explanation: Imposed deadlines a...

View Answer

An activity's normal time and cost are 5 and $40, respectively.Its estimated crash time and cost are 4 and $70, respectively.This activity's crash cost per time unit is ________.

Correct Answer

verifed

verified

$30
Explanation: Crash cost pe...

View Answer

Which of the following is NOT one of the more commonly used options for cutting project costs?


A) Reduce project scope
B) Have owner take more responsibility
C) Move the completion date further out
D) Brainstorm cost savings options
E) Outsource project activities

Correct Answer

verifed

verified

Which of the following is NOT a technique for accelerating project completion when resources are not constrained?


A) Assign additional staff and equipment
B) Establish a core team
C) Do it twice-first fast and then correctly
D) Reduce project scope
E) Compromise quality

Correct Answer

verifed

verified

Before crashing, direct costs for an activity represent normal costs, which typically mean low-cost, efficient methods for completing the activity in a(n) ________ amount of time.


A) Normal
B) Budgeted
C) Optimized
D) Expected
E) Targeted

Correct Answer

verifed

verified

Reducing project duration


A) Involves crashing all activities to their crash point.
B) Can only be done when resources are not constrained.
C) Is always more expensive.
D) Tends to increase network sensitivity.
E) Should be considered for all projects.

Correct Answer

verifed

verified

The shortest possible time an activity can be completed realistically is called ___­­­_____ time.


A) Expedited
B) Accelerated
C) Crash
D) Optimistic
E) Optimal

Correct Answer

verifed

verified

In a Project Cost-Duration Graph, total project costs are a sum of


A) Labor, material and equipment costs.
B) Direct costs plus interest.
C) Direct labor costs and the project manager's salary.
D) Direct costs and the project manager's salary.
E) Direct and indirect costs.

Correct Answer

verifed

verified

Costs such as labor, materials, equipment, or contractors are examples of ________ project costs.

Correct Answer

verifed

verified

direct
Explanation: Direct cos...

View Answer

Direct costs are assignable directly to a particular ________.

Correct Answer

verifed

verified

work package
Explanation: Dire...

View Answer

Given an equal level of risk and the need to reduce overall project duration, why would you NOT select the activity with the least slope, in the entire project network, to crash first?

Correct Answer

verifed

verified

If it is not on the critical path crashing it will not reduce project duration.

A reasonable, quick comparison between options for compressing activity times is based upon a _______________ assumption.

Correct Answer

verifed

verified

linear
Explanation: For most manager, a ...

View Answer

Insensitive networks are a rarity; Planning for a sensitive network is more practical.

Correct Answer

verifed

verified

Because direct costs are assumed to be developed from "normal" methods and in a "normal" amount of time, any reduction in activity time should add to the costs of the activity.

Correct Answer

verifed

verified

The direct cost for completing an activity as early as possible is called its ________ cost.

Correct Answer

verifed

verified

crash Explanation: The direct cost for completing an activity in its crash time is called crash cost.Both normal and crash times and costs are collected from personnel most familiar with completing the activity.

Intense global competition and rapid technological advances combine to create a(n)________-imposed project duration date.

Correct Answer

verifed

verified

market
Explanation: Intense global compe...

View Answer

Crashing activities on a project network that is sensitive could increase the risk of the project being late.

Correct Answer

verifed

verified

Shortening an activity's duration is termed crashing.

Correct Answer

verifed

verified

True

One way of reducing project costs is identifying tasks that _________ can do themselves.

Correct Answer

verifed

verified

customers
Explanation: When co...

View Answer