When resource constraints are added to technical constraints the original project network may change as well as the completion date.

Correct Answer

verifed

verified

Comparing Planned Costs versus Actual Costs will give the project manager a quick understanding of the status of the project.

Correct Answer

verifed

verified

Jan is trying to reallocate resources in a time-constrained project to create smoother resource utilization.She should first identify activities with the


A) Smallest duration.
B) Least slack.
C) Most slack.
D) Lowest identification number.
E) Highest cost.

Correct Answer

verifed

verified

List and briefly describe the disadvantages of resource leveling or smoothing.

Correct Answer

verifed

verified

(1)Loss of flexibility.
(2)Inc...

View Answer

The inability to fit more than two earth movers on a construction site at the same time when more are needed to complete the activity on time is an example of a physical constraint.

Correct Answer

verifed

verified

Resource dependency takes priority over technological dependency but it does not violate it.

Correct Answer

verifed

verified

All leveling techniques delay noncritical activities by using ________ to reduce peak demand.

Correct Answer

verifed

verified

positive slack
Explanation: Al...

View Answer

A project cost baseline is also called __________.

Correct Answer

verifed

verified

planned value (PV
Explanation: The outco...

View Answer

In a resource-constrained project the second priority in assigning resources is usually given to activities with the


A) Smallest duration.
B) Least slack.
C) Most slack.
D) Lowest identification number.
E) Highest cost.

Correct Answer

verifed

verified

These are all guidelines a project manager should consider when EXCEPT


A) Select people with compatible work habits and personalities.
B) Always assign the best people to the most difficult tasks.
C) When possible, team veterans up with new hires.
D) Select individuals with skillsets that complement each other.
E) Have people work together early so that they can become familiar with each other.

Correct Answer

verifed

verified

Having one person responsible for performing several activities, all due at the same time, is an example of a(n)________ constraint.

Correct Answer

verifed

verified

resource
Explanation: If one p...

View Answer

Why is a schedule not a schedule until resources have been assigned? Provide a real life example that illustrates your explanation.

Correct Answer

verifed

verified

Before resources are assigned it is assu...

View Answer

Rachel is working on a project that technically allows three activities to be done at the same time.If they were to be implemented at the same time, she would need 5 contractors in order for the activities to be completed on time.There are only 3 available for her to use.This is an example of what type of constraint?


A) Technical
B) People
C) Equipment
D) Physical
E) Materials

Correct Answer

verifed

verified

A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000.We can assume that everything is going as planned and that we are under budget.

Correct Answer

verifed

verified

To determine if a project is time-constrained or resource-constrained you would consult the project priority matrix.

Correct Answer

verifed

verified

When a project is classified as resource-constrained and a resource constraint exists, the project duration is typically __________.

Correct Answer

verifed

verified

extended
Explanation: If resources are n...

View Answer

Most of the scheduling methods available today require the project manager to classify the project as either _______ constrained or ______ constrained.


A) Time, quality
B) Quality, resource
C) Cost, time
D) Quality, cost
E) Time, resource

Correct Answer

verifed

verified

Since resource leveling or smoothing delays noncritical activities, a common result is a decrease in network sensitivity.

Correct Answer

verifed

verified

When leveling schedules to overcome resource constraints, ___________ is increased.


A) impact of risks
B) scheduling complexity
C) cost
D) amount of available slack

Correct Answer

verifed

verified

Delaying noncritical activities to lower peak demand and, thus, increase resource utilization is called resource __________.

Correct Answer

verifed

verified

Levelling or smoothing
Explanation: Prac...

View Answer