Filters
Question type

Study Flashcards

What is sometimes humorously referred to as a "gozinto chart"?


A) Assembly drawing
B) Assembly chart
C) Process flowchart
D) Operation and route sheet
E) Organization charts

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

The most common production management tools used in planning and designing the process flow are assembly drawings,assembly charts,route sheets and flow process charts.

A) True
B) False

Correct Answer

verifed

verified

A manufacturer has identified the options for acquiring a machined part.It can make the part on a numerically controlled lathe for $150 per unit (including materials. )It can make the part on a standard lathe for $250 per unit (also including materials. )It can make the part on a machining center for $50 per unit (also including materials. )The manufacturer can acquire a standard lathe for $10,000.It could acquire a numerically controlled lathe for $100,000.A machining center would cost $350,000.It has also found that it can purchase the part for $350 per unit?

Correct Answer

verifed

verified

If the quantity required is less than 100,purchase the part for $350 per unit.If the quantity needed is between 100 and 900,use the standard lathe.If the quantity needed is more than 900 but less than 2,500,use the numerically controlled lathe.If the quantity needed was greater than 2,500,the machining center is best. (Std vs NC:$250*D+$10,000=$150*D+$100,000;$100*D=$90,000;D=900) (Buy vs.Std:$350*D=$10,000+250*D;$100*D=$10,000;D=100) (NC vs.Machining Ctr:$150*D+$100,000=$50*D+$350,000;$100*D=$250,000;D=2,500)

Which of the following basic types of process structures is one which similar equipment or functions are grouped together?


A) Project
B) Workcenter
C) Manufacturing cell
D) Assembly line
E) Continuous process

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

Which of the following is not considered a major process flow structure?


A) Project
B) Workcenter
C) Assembly line
D) Fabrication
E) Continuous Flow

F) All of the above
G) B) and D)

Correct Answer

verifed

verified

Process selection refers to the strategic decision of choosing the volume of output to produce in a manufacturing facility depending upon the way that facility produces.

A) True
B) False

Correct Answer

verifed

verified

The product-process matrix shows the relationship between process structures and product volume.

A) True
B) False

Correct Answer

verifed

verified

The choice of which process structure to select is generally a function of the volume requirements for the product.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not a basic type of process structure?


A) Product-process matrix
B) Workcenter
C) Manufacturing cell
D) Assembly line
E) Continuous process

F) C) and D)
G) A) and D)

Correct Answer

verifed

verified

Differentiate between a workcenter and a manufacturing cell?

Correct Answer

verifed

verified

These layout types are discussed on page...

View Answer

A process flowchart uses the information presented in the assembly drawing and defines how parts go together and their order of assembly.

A) True
B) False

Correct Answer

verifed

verified

The choice of which process structure to select is generally a function of the volume requirements for the product.

A) True
B) False

Correct Answer

verifed

verified

Give an example of a project layout?

Correct Answer

verifed

verified

A construction proje...

View Answer

Which of the following basic types of process structures is one which equipment or work processes are arranged according to the progressive steps by which the product is made?


A) Project
B) Workcenter
C) Manufacturing cell
D) Assembly line
E) Continuous process

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

Once a choice of position on the product-process matrix is selected change is impossible.

A) True
B) False

Correct Answer

verifed

verified

False

Assume a fixed cost for a process of $100,000.The variable cost to produce each unit of product is $10 and the selling price for the finished product is $50.Ignoring inventory,how many units must the firm sell to break-even?

Correct Answer

verifed

verified

You are hired as a consultant to decide if your client should purchase a new,highly specialized,piece of equipment.The product to be produced by this equipment is forecast to have a total world wide demand of 15,000 units over the entire product life.The initial investment to acquire and install the equipment is $256,000.The variable cost to produce each unit will be $15 and the selling price for the finished product will be $30.Which of the following best describes the situation the firm is facing?


A) The company will recover its' initial investment
B) The company's total margin will be less than its' investment
C) It's a good investment
D) The break-even is lower than the 15,000 units that are expected to sell
E) All of the above

F) A) and C)
G) C) and E)

Correct Answer

verifed

verified

In a factory,machine A has a ten minute set-up time per batch and a two minute per unit run time.Machine B performs the identical function but has a set-up time of thirty minutes and a one minute run time per unit.The factory makes products in batches ranging from one unit to one hundred units.Assuming capacity is not a limitation on either machine,on which batches should machine B be used?


A) All batches should be run on machine B
B) Batches of more than 20 units should be run on machine B
C) Batches of fewer than 80 units should be run on machine B
D) Batches with up to 50 units should be run on machine B
E) No batches should be run on machine B

F) B) and E)
G) C) and D)

Correct Answer

verifed

verified

Describe the implications of the product-process matrix for process design in a competitive situation?

Correct Answer

verifed

verified

The product-process matrix on page 207 i...

View Answer

One methodology used to evaluate equipment investment decisions where the investment entails a large initial investment,fixed costs and variable costs is break-even analysis.

A) True
B) False

Correct Answer

verifed

verified

True

Showing 1 - 20 of 42

Related Exams

Show Answer