Filters
Question type

Study Flashcards

If the LP relaxation of an integer program has a feasible solution,then the integer program has a feasible solution.

Correct Answer

verifed

verified

Solve the following problem graphically.  Max 5x+6y s.t. 17x+8y1363x+4y36x,y0 and integer \begin{array} { l l } \text { Max } & 5 x + 6 y \\\text { s.t. } & 17 x + 8 y \leq 136 \\& 3 x + 4 y \leq 36 \\& x , y \geq 0 \text { and integer }\end{array} a.Graph the constraints for this problem. Indicate all feasible solutions. b.Find the optimal solution to the LP Relaxation. Round down to find a feasible integer solution. Is this solution optimal? c.Find the optimal solution.

Correct Answer

verifed

verified

a.The feasible region is those integer v...

View Answer

Given the following all-integer linear program: Max 15x1+2x215 x _ { 1 } + 2 x _ { 2 } s. t. 7x1+x2237 x _ { 1 } + x _ { 2 } \leq 23 3x1x253 x _ { 1 } - x _ { 2 } \leq 5 x1,x20x _ { 1 } , x _ { 2 } \geq 0 and integer a. Solve the problem as an LP, ignoring the integer constraints. b. What solution is obtained by rounding up fractions greater than or equal to 1/2? Is this the optimal integer solution? c. What solution is obtained by rounding down all fractions? Is this the optimal integer solution? Explain. d. Show that the optimal objective function value for the ILP is lower than that for the optimal LP. e. Why is the optimal objective function value for the ILP problem always less than or equal to the corresponding LP's optimal objective function value? When would they be equal? Comment on the MILP's optimal objective function compared to the corresponding LP & ILP.

Correct Answer

verifed

verified

a.x1 = 2.8,x2 = 3.4,Obj.func.= 48.8
b.x1 = ...

View Answer

Kloos Industries has projected the availability of capital over each of the next three years to be $850,000,$1,000,000,and $1,200,000,respectively.It is considering four options for the disposition of the capital: (1)Research and development of a promising new product (2)Plant expansion (3)Modernization of its current facilities (4)Investment in a valuable piece of nearby real estate Monies not invested in these projects in a given year will NOT be available for following year's investment in the projects.The expected benefits three years hence from each of the four projects and the yearly capital outlays of the four options are summarized in the table below in $1,000,000's. In addition,Kloos has decided to undertake exactly two of the projects,and if plant expansion is selected,it will also modernize its current facilities.  Capital Outlays  Projected  Options  Year 1  Year 2  Year 3  B enefits  New Product R&D .35.55.755.2 Plant Expansion .50.5003.6 Modernization .35.40.453.2 Real Estate .50002.8\begin{array} { l c c c c } & { \text { Capital Outlays } } &&& \text { Projected } \\\text { Options } & \text { Year 1 } & \text { Year 2 } & \text { Year 3 } & \text { B enefits } \\\hline \text { New Product R\&D } & .35 & .55 & .75 & 5.2 \\\text { Plant Expansion } & .50 & .50 & 0 & 3.6 \\\text { Modernization } & .35 & .40 & .45 & 3.2 \\\text { Real Estate } & .50 & 0 & 0 & 2.8\end{array} Formulate and solve this problem as a binary programming problem.

Correct Answer

verifed

verified

The classic assignment problem can be modeled as a 0-1 integer program.

Correct Answer

verifed

verified

The product design and market share optimization problem presented in the textbook is formulated as a 0-1 integer linear programming model.

Correct Answer

verifed

verified

Most practical applications of integer linear programming involve only 0 - 1 integer variables.

Correct Answer

verifed

verified

Rounded solutions to linear programs must be evaluated for


A) feasibility and optimality.
B) sensitivity and duality.
C) relaxation and boundedness.
D) each of these choices are true.

Correct Answer

verifed

verified

Why are 0 - 1 variables sometimes called logical variables?

Correct Answer

Answered by ExamLex AI

Answered by ExamLex AI

0 - 1 variables are sometimes called log...

View Answer

Hansen Controls has been awarded a contract for a large number of control panels.To meet this demand,it will use its existing plants in San Diego and Houston,and consider new plants in Tulsa,St.Louis,and Portland.Finished control panels are to be shipped to Seattle,Denver,and Kansas City.Pertinent information is given in the table.  Shipping Cost to Destination:  Sources  Construction  Cost  Seattle  Denver  Kansas  City  Capacity  San Diego 5782,500 Houston 10862,500 Tulsa 350,00094310,000 St. Louis 200,000126210,000 Portland 480,0004101110,000 Demand 3,0008,0009,000\begin{array} { l | c | c c c | c } & &{ \text { Shipping Cost to Destination: } } & \\{ \text { Sources } } & \begin{array} { c } \text { Construction } \\\text { Cost }\end{array} & \text { Seattle } & \text { Denver } & \begin{array} { c } \text { Kansas } \\\text { City }\end{array} & \text { Capacity } \\\hline \text { San Diego } & \cdots & 5 & 7 & 8 & 2,500 \\\text { Houston } & \cdots & 10 & 8 & 6 & 2,500 \\\text { Tulsa } & 350,000 & 9 & 4 & 3 & 10,000 \\\text { St. Louis } & 200,000 & 12 & 6 & 2 & 10,000 \\\text { Portland } & 480,000 & 4 & 10 & 11 & 10,000 \\\hline & \text { Demand } & 3,000 & 8,000 & 9,000 &\end{array} Develop a model whose solution would reveal which plants to build and the optimal shipping schedule.

Correct Answer

verifed

verified

Integer linear programs are harder to solve than linear programs.

Correct Answer

verifed

verified

Modeling a fixed cost problem as an integer linear program requires


A) adding the fixed costs to the corresponding variable costs in the objective function.
B) using 0-1 variables.
C) using multiple-choice constraints.
D) using LP relaxation.

Correct Answer

verifed

verified

Some linear programming problems have a special structure that guarantees the variables will have integer values.

Correct Answer

verifed

verified

Solve the following problem graphically.  Min 6x+11y s.t. 9x+3y277x+6y424x+8y32x,y0 and integer \begin{array} { l l } \text { Min } & 6 x + 11 y \\\text { s.t. } & 9 x + 3 y \geq 27 \\& 7 x + 6 y \geq 42 \\& 4 x + 8 y \geq 32 \\& x , y \geq 0 \text { and integer }\end{array} a.Graph the constraints for this problem. Indicate all feasible solutions. b.Find the optimal solution to the LP Relaxation. Round up to find a feasible integer solution. Is this solution optimal? c.Find the optimal solution.

Correct Answer

verifed

verified

a.The feasible region is the set of inte...

View Answer

Generally,the optimal solution to an integer linear program is less sensitive to the constraint coefficients than is a linear program.

Correct Answer

verifed

verified

A multiple choice constraint involves selecting k out of n alternatives,where k 2.

Correct Answer

verifed

verified

Solve the following problem graphically. Maxx+2y s.t. 6x+8y487x+5y35x,y0 and y is integer \begin{array} { l l } \operatorname { Max } & x + 2 y \\\text { s.t. } & 6 x + 8 y \leq 48 \\& 7 x + 5 y \geq 35 \\& x , y \geq 0 \text { and } y \text { is integer }\end{array} a.Graph the constraints for this problem. Indicate all feasible solutions. b.Find the optimal solution to the LP Relaxation. Round down to find a feasible integer solution. Is this solution optimal? c.Find the optimal solution.

Correct Answer

verifed

verified

a.The feasible region consists of the po...

View Answer

Slack and surplus variables are not useful in integer linear programs.

Correct Answer

verifed

verified

Grush Consulting has five projects to consider.Each will require time in the next two quarters according to the table below.  Project  Time in first quarter  Time in second quarter  Revenue  A 5812000 B 31210000 C 7515000 D 235000 E 15120000\begin{array} { c c c c } \text { Project } & \text { Time in first quarter } & \text { Time in second quarter } & \text { Revenue } \\\hline \text { A } & 5 & 8 & 12000 \\\text { B } & 3 & 12 & 10000 \\\text { C } & 7 & 5 & 15000 \\\text { D } & 2 & 3 & 5000 \\\text { E } & 15 & 1 & 20000\end{array} Revenue from each project is also shown.Develop a model whose solution would maximize revenue,meet the time budget of 25 in the first quarter and 20 in the second quarter,and not do both projects C and D.

Correct Answer

verifed

verified

Let A = 1 if project...

View Answer

Give a verbal interpretation of each of these constraints in the context of a capital budgeting problem. a.x1 x2 0 b.x1 x2 = 0 c.x1 + x2 + x3 2

Correct Answer

Answered by ExamLex AI

Answered by ExamLex AI

a. The first constraint states that the ...

View Answer

Showing 21 - 40 of 61

Related Exams

Show Answer