A) they should exceed the amount of funds available.
B) they cannot exceed the total project budgeted cost.
C) if the total is too high then the amounts should be force-fitted into the customer's budget.
D) if the total is too low then extra non-project expenses should be added.
Correct Answer
verified
Multiple Choice
A) total budgeted cost TBC)
B) cumulative budgeted cost CBC)
C) cumulative actual cost CAC)
D) cumulative earned value CEV)
Correct Answer
verified
Multiple Choice
A) total budgeted cost TBC)
B) cumulative budgeted cost CBC)
C) cumulative actual cost CAC)
D) cumulative earned value CEV)
Correct Answer
verified
Multiple Choice
A) that the organization wants to have.
B) that is the latest upgrade, even if not needed for the project.
C) that must be purchased as part of the project.
D) needed by others in the organization that may not be assigned to the project.
Correct Answer
verified
Multiple Choice
A) provide frequent payments, such as weekly or monthly payments rather than quarterly payments.
B) make equal monthly payments based on the expected duration of the project.
C) make a single payment at the end of the project.
D) provide a down payment at the start of the project.
Correct Answer
verified
Multiple Choice
A) planned cost, total budgeted cost.
B) budgeted cost of work scheduled, actual cost of work performed.
C) actual cost, cumulative budgeted cost.
D) cumulative earned value, total budgeted cost.
Correct Answer
verified
Multiple Choice
A) audits the amounts assigned.
B) periodically assigns a portion of their total cost to actual cost.
C) enters the amount of the cost one time at the end of the project.
D) enters the amount of the cost one time at the beginning of the project.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) you have enough money to cover the costs of performing the project.
B) you hold a reserve of funds instead of paying bills.
C) payroll can be paid and suppliers are delayed indefinitely.
D) deposits can be made in several different accounts.
Correct Answer
verified
Multiple Choice
A) initiating
B) planning
C) performing
D) closing
Correct Answer
verified
Multiple Choice
A) total budgeted cost TBC)
B) cumulative budgeted cost CBC)
C) cumulative earned value CEV)
D) cumulative actual cost CAC)
Correct Answer
verified
Multiple Choice
A) Resource analysis
B) CPI monitoring
C) Cost control
D) Problem solving
Correct Answer
verified
Multiple Choice
A) assign each TBC at the start of its work package.
B) assign each TBC at the end of its work package.
C) distribute each TBC over the project by dividing the total by the number of work packages and assigning that amount to each.
D) distribute each TBC over the duration of its work package.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $10
B) -$10
C) 0.5
D) 2.0
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) cumulative budget
B) total budget
C) budget at completion
D) phased budget
Correct Answer
verified
Multiple Choice
A) what work should have been done.
B) what work remains to be done.
C) what work others have to do on other projects.
D) the cost of the work.
Correct Answer
verified
True/False
Correct Answer
verified
Showing 21 - 40 of 69
Related Exams