Filters
Question type

Study Flashcards

Which one of the following capital budgeting decision methods measures how long it takes for a project's benefits to recover the project's cost?


A) profitability index
B) payback period
C) modified internal rate of return
D) net present value

Correct Answer

verifed

verified

Which of the following is true for a project with an expected net present value of $200,000?


A) The project is clearly unacceptable.
B) The project's cash flows exceed the project's net investment by $200,000 annually.
C) The project is expected to increase firm value by $200,000 in future value terms.
D) The project is expected to increase firm value by $200,000 in present value terms.

Correct Answer

verifed

verified

A capital budgeting project has a net investment of $450,000 and is expected to generate net cash flows of $150,000 annually for 5 years. What is the net present value at a 15% required rate of return?


A) $64,962
B) $52,823
C) $41,144
D) $300,000

Correct Answer

verifed

verified

Which of the following is not true of the payback period method?


A) It fails to take into account the time value of money.
B) It fails to take into account a project's net cash flows.
C) It fails to take into account a project's net cash flows after the payback period.
D) There is no objective criterion for what is an acceptable payback period.

Correct Answer

verifed

verified

If a project is normal, which of the following is true for a project with an internal rate of return exceeding the required rate of return?


A) The net present value is negative
B) The net present value is zero
C) The net present value is positive
D) There is not enough information to determine anything about the project's net present value.

Correct Answer

verifed

verified

If a project's net present value is positive negative), the project is generally acceptable unacceptable).

Correct Answer

verifed

verified

Which of the following is true about the net present value method?


A) It is the best single measure of a project's profitability.
B) It is the best single measure of a project's overall risk.
C) It is the best single measure of a project's liquidity risk.
D) It is not a good measure of a project's profitability.

Correct Answer

verifed

verified

A capital budgeting project is expected to have the following cash flows: A capital budgeting project is expected to have the following cash flows:    What is the project's payback period? A) 1.50 years B) 3.30 years C) 2.50 years D) 2.30 years What is the project's payback period?


A) 1.50 years
B) 3.30 years
C) 2.50 years
D) 2.30 years

Correct Answer

verifed

verified

A capital budgeting project is expected to have the following cash flows: A capital budgeting project is expected to have the following cash flows:    What is the project's net present value at an 18% required rate of return? A) -$4,173.50 B) $10,800.96 C) -$18,725.33 D) $350,000.00 What is the project's net present value at an 18% required rate of return?


A) -$4,173.50
B) $10,800.96
C) -$18,725.33
D) $350,000.00

Correct Answer

verifed

verified

If a capital budgeting project's cash flows are not normal, the internal rate of return method should be used to make the investment decision.

Correct Answer

verifed

verified

Showing 21 - 30 of 30

Related Exams

Show Answer