Consider a project having the following seven activities: Consider a project having the following seven activities:     (a) What is the expected time for each activity? (b) What is the expected project completion time? (c) What is the critical path? (d) What is the variance for each activity? (e) What are the expected time and variance of each path? (f) What is the probability that the project will be completed in less than 24 weeks? (a) What is the expected time for each activity? (b) What is the expected project completion time? (c) What is the critical path? (d) What is the variance for each activity? (e) What are the expected time and variance of each path? (f) What is the probability that the project will be completed in less than 24 weeks?

Correct Answer

verifed

verified

(a) A - 3 weeks, B - 4.67 weeks, C - 5 w...

View Answer

For projects whose activities have probabilistic time estimates, the probability of completing the project in a specified amount of time is determined by __________________________.


A) the expected time for the critical path only
B) the standard deviation for the critical path only
C) the expected time and standard deviation for the critical path only
D) the expected times for all paths
E) the expected times and standard deviations for the critical path and paths whose expected times are close to that of the critical path

Correct Answer

verifed

verified

Which phase in the project life cycle involves ending the project?


A) conception
B) feasibility analysis or study
C) planning
D) execution
E) termination

Correct Answer

verifed

verified

Crashing a schedule is reducing a project completion time by ___________________.


A) renegotiating with management
B) realign tasks in parallel
C) rearranging all tasks
D) throwing additional resources to the critical path
E) throwing less resources to the critical path

Correct Answer

verifed

verified

Joe's tower fabrication company client would like to know what the probability is of completing the project in 60 days rather than the 58 estimated days. Based on Z values what is the probability that Joes' tower fabrication will be able to meet the request if the variance is 1.25?


A) -1.6
B) 1.6
C) -1.79
D) 1.79
E) 2

Correct Answer

verifed

verified

The critical path is the sequential path of interrelated activities which has the ____________________.


A) most activities
B) longest time
C) most nodes
D) most events
E) most arrows

Correct Answer

verifed

verified

In making a forward pass through a network, activities L, M, and P are immediate predecessors for activity T, which has an activity time of 7. The early start times for activities L, M, and P are 22, 17, and 27, respectively. The early finish times for activities L, M, and P are 29, 27, and 33, respectively. What is the early finish time for activity T?


A) 17
B) 24
C) 27
D) 33
E) 40

Correct Answer

verifed

verified

The purpose of change control boards is to review and prioritize changes during the course of a project.

Correct Answer

verifed

verified

In making a backward pass through a network, activity T immediately precedes three activities. What is the late finish time for activity T?


A) the smallest LS for the three activities that activity T immediately precedes
B) the largest LS for the three activities that activity T immediately precedes
C) the smallest LF for the three activities that activity T immediately precedes
D) the largest LF for the three activities that activity T immediately precedes
E) the activity time for activity T

Correct Answer

verifed

verified

A project schedule is a tool used to communicate what work needs to be performed, which resources are used to perform the work, and when the work needs to be performed.

Correct Answer

verifed

verified

What are the benefits of network planning techniques?

Correct Answer

verifed

verified

graphical display of the project, includ...

View Answer

Deterministic time estimate makes a _______________ time estimate for each project ___________.

Correct Answer

verifed

verified

Projects vary in terms of objectives but each has a _______________ of activities.

Correct Answer

verifed

verified

The last project activity ES and LS times are:


A) different
B) calculated using termination rules
C) the same
D) required probabilistic calculations
E) involving risk analysis

Correct Answer

verifed

verified

In critical path scheduling, slack is computed as the difference between ______________________.


A) latest and earliest times
B) optimistic and pessimistic times
C) mean and modal times
D) finish and start times
E) observed and predicted times

Correct Answer

verifed

verified

A feeder buffer protects a ______ path from delays in a __________.


A) shortest, buffer overflow
B) noncritical, critical path
C) critical, noncritical path
D) critical, longest variance
E) noncritical, longest variance

Correct Answer

verifed

verified

Consider a project having the following seven activities: Consider a project having the following seven activities:     (a) What is the expected project completion time? (b) What is the critical path? (c) What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks? By five weeks? (a) What is the expected project completion time? (b) What is the critical path? (c) What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks? By five weeks?

Correct Answer

verifed

verified

(a) 26 weeks; (b) A-B-D-F-G; (c) three w...

View Answer

What are the steps involved in using network planning techniques?

Correct Answer

verifed

verified

(1) Describe the project. (2) ...

View Answer

An activity in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 15 days. Its expected time is _________________.


A) 5 days
B) 7 days
C) 8 days
D) 10 days
E) 15 days

Correct Answer

verifed

verified

What are valid reasons for reducing the time spent finishing a particular project?

Correct Answer

verifed

verified

deadlines, promised completion...

View Answer